APPLICATIONS

Masonry with BlokBims Products

  • Before starting the wall application, the floor must be smooth and the level of the wall should be leveled with Block Bims. A leveling layer is applied with a cement-mortar mortar on a clean and scoured floor.
  • A corner is placed on each corner by placing a BLOCK BIMS bimsblok.
  • On the ground level, BLOK BIMS is placed in the first row by starting from one corner to the placement of the bimsblocks.
  • If the mortar pocketed products are used in the wall application, mortar should be placed on vertical joints and vertical spacing should be left in the vertical.
  • In vertical wall blocks, no mortar grout is applied.
  • After the BLOCK BIMM wall block has been placed in place, it should be smoothed with rubber hammer.
  • The mortar is applied on the blocks to form a horizontal connection joint. Joint thickness should be maximum 7-10mm.
  • In the walling, the overlap of the blocks must be in the ratio of 1/2 of the block.
  • If necessary, the blocks can be cut to a smaller size.
  • No space between the wall and the column should be filled with mortar.
  • There should be 1-2cm gap between the wall and the surface of the wall at the connection with the wall. These gaps should be filled with polyurethane foam or mortar.